The statement that propositionalisation is an efficient, sound, and complete procedure for inference in First Order Logic is false.
Propositionalisation is a process that involves replacing a First Order Logic (FOL) sentence with an equivalent Propositional Logic (PL) sentence. Propositional Logic is a simpler form of logic that deals only with propositions or statements that can be either true or false. In contrast, First Order Logic deals with more complex statements that include variables, quantifiers, and predicates.While propositionalisation may be useful in certain cases, it is not an efficient, sound, or complete procedure for inference in First Order Logic. Here's why:Efficiency: Propositionalisation can lead to an explosion in the size of the resulting PL sentence. This means that the number of propositions can become so large that the process becomes computationally infeasible, even for relatively simple FOL sentences. As a result, propositionalisation is not generally considered to be an efficient procedure for inference in FOL.Soundness: Propositionalisation can lead to the loss of important information that is present in the original FOL sentence. This means that the resulting PL sentence may not accurately represent the intended meaning of the original FOL sentence. As a result, propositionalisation is not a sound procedure for inference in FOL.Completeness: Propositionalisation is not a complete procedure for inference in FOL. This means that there are certain inferences that cannot be made using propositionalisation alone. For example, propositionalisation cannot handle statements that involve quantifiers, such as "For all x, P(x)". In order to make such inferences, a more powerful logic such as Second Order Logic or Higher Order Logic is needed.
To know more about Logic visit:
brainly.com/question/31835546
#SPJ11
1. A drilling operation is to be performed with a 10 mm diameter twist drill in a steel workpart. The hole is a blind hole at a depth of 60 mm and the point angle is 118. The cutting speed is 30 m/min and the feed is 0.25 mm/rev. Determine (a) the cutting time to complete the drilling operation, and (b) metal removal rate during the operation, after the drill bit reaches full diameter.
Answer:
The answer is below
Explanation:
v = velocity = 30 m/min = 30 * 10³ mm/min, D = diameter = 10 mm, f = feed = 0.25 mm/rev, point angle = 118, cutting time = Tm, d = depth = 60 mm
\(a)\\N=\frac{v}{\pi D}=\frac{30*10^3}{\pi * 10}=954.9\ rev/min\\\\f_r=Nf =954.9(0.25)=238\ mm/min\\\\A=0.5Dtan(90-\frac{point\ angle}{2} )=0.5*10*tan(90-\frac{118}{2} )=3\ mm\\\\T_m=\frac{(d+A)}{f_r} =\frac{60+3}{238}=0.265 \ s\\\\b)\\metal\ removal\ rate(R_{MR})=0.25\pi D^2f_r\\\\R_{MR}=0.25\pi (10)^2(238)=18692\ mm^3/min\)
* Question 1: Design alarm system as shown below. The alarm turns on when one of the following
conditions happened:
A. Motion IR sensor & window sensor
activated.
B. Motion IR sensor & door sensor
activated.
C. Otherwise the buzzer off.
(A)
Warning
Motion
Sensors
Buzzer
Suppose that: Warning buzzer on pin 8
Motion sensor on pin 5
Window sensor on pin 6
Door sensor on pin 7
The buzzer works on beating mode.
(C)
Door
sensor
TE
(B)
Window
Sensors
Answer:
A
Explanation:
GMA MIG weiding is a
Gas metal arc welding (GMAW), sometimes referred to by its subtypes metal inert gas (MIG) welding or metal active gas (MAG) welding, is a welding process in which an electric arc forms between a consumable MIG wire electrode and the workpiece metal(s), which heats the workpiece metal(s), causing them to melt and join.
Explanation:
GMA MIG weiding is aiejrjjrkdkff
The scale of the blueprint tells us the
of drawing to real space?
Answer:
yes
Explanation:
blueprint of the construction is a prediction of project its is slightly auto cad
What is the importance of food handling machines in food industry (Explain in points).
Answer:
Explanation:
Profile photo for Rosie Milojevic
Rosie Milojevic, Business Development at iComplied
Answered 3 years ago
For those who run or work in a business that handles food, you understand the importance of food safety and regulation compliance as it pertains to not only to certification and licensing of a company, but also the life or death of those who consume the products. Because food safety is such an important issue, we want to ensure that all companies who work in the production, preparation, or processing of food have the tools and information they need to ensure they are in full compliance 100% of the time. One slip in food safety compliance could cost someone their health or life, and this information spreads mistrust in the general public toward the company who sold the product, and also the entire product across companies throughout an entire country and beyond. So how does each company working with food ensure they comply with each and every food safety regulation? Through excellent auditing tools.
Auditing in Food Safety Must Change
Auditing in food safety compliance is essential in ensuring that all regulations are being complied with. Most auditing practices for major companies are severely out of date. Many rely on several different forms, stacks of paperwork, and data stored on multiple different computers and databases. This is incredibly inefficient, as it can be easy to miss something when comparing one sheet to the next, and paper can easily be lost or destroyed. It is also time consuming for companies to share audits over separate computers and databases, as it must be passed down from one employee to the next. Technology has granted all food safety compliance managers a simple solution. Auditing apps are the new wave solutions for companies who want all of their data stored on one cloud database that is instantly accessible with real-time data for all employees. This means that no one ever gets left out of the loop, and no new information will fall through the cracks.
Two Electric field vectors E1 and E2 are perpendicular to each other; obtain its base
vectors.
Answer:
<E1, E2>.
Explanation:
So, in the question above we are given that the Two Electric field vectors E1 and E2 are perpendicular to each other. Thus, we are going to have the i and the j components for the two Electric Field that is E1 and E2 respectively. That is to say the addition we give us a resultant E which is an arbitrary vector;
E = |E| cos θi + |E| sin θj. -------------------(1).
Therefore, if we make use of the components division rule we will have something like what we have below;
x = |E2|/ |E| cos θ and y = |E1|/|E| sin θ
Therefore, we will now have;
E = x |E2| i + y |E1| j.
The base vectors is then Given as <E1, E2>.
A capacitor is connected into a 1250v 1000hz circuit. The current is 80A. What is the capacitance of the capacitor
QUESTION 6 Assignment C. Kobils Engineering Company wishes to employ a qualified foreman to oversee operations at its plant. The right person must have the following requirements: . Grade 12 School Certificate with five "O" levels. . Advanced Certificate in a relevant engineering field. 1 . Minimum of two years working experience. : Member of EIZ Prepare a detailed Curriculum Vitae for the position, include any other relevant details. Assignment 2 (20 marks)
The Curriculum Vitae (CV) for the foreman position should include Grade 12 School Certificate, relevant engineering certification, work experience, and EIZ membership.
Curriculum Vitae (CV) for the position of a qualified foreman at Kobils Engineering Company:
Personal Information: Include your full name, contact details (phone number, email address, residential address), and date of birth.
Objective:State your career objective as a qualified foreman, highlighting your commitment to overseeing operations efficiently and effectively.
Education:Grade 12 School Certificate with five "O" levels.
Advanced Certificate in a relevant engineering field. Specify the specific engineering field and the institution where you obtained the certificate.
Work Experience:Provide details of your work experience, emphasizing relevant roles where you demonstrated leadership, problem-solving, and organizational skills. Include the company name, job title, duration of employment, and key responsibilities.
Minimum of two years of working experience should be mentioned.
Professional Memberships:Mention your membership in the Engineering Institute of Zambia (EIZ) as it demonstrates your commitment to professional development and adherence to industry standards.
Skills:Highlight your technical skills and knowledge relevant to the foreman role, such as project management, team coordination, quality control, and adherence to safety regulations.
Achievements:Include any notable achievements or awards related to your engineering career, such as successful project completions or improvements in operational efficiency.
References:Provide the names, designations, contact details, and professional relationships of individuals who can provide references attesting to your qualifications and work ethic.
Remember to format the CV professionally, include accurate and up-to-date information, and tailor it to showcase your qualifications and experience specifically for the foreman position at Kobils Engineering Company.
For more questions on certification
https://brainly.com/question/19393940
#SPJ8
How do you replace old weather stripping on a door?
Replacing old weather stripping on a door is a straightforward process that can help improve your home's energy efficiency.
Here are the steps to replace old weather stripping on a door:
Remove the Old Weather Stripping To remove the old weather stripping, use a putty knife to loosen the adhesive or nails that hold the stripping in place. Once the weather stripping is loose, you can remove it by pulling it off the door.
Clean the Door Surface After removing the old weather stripping, clean the door surface thoroughly. This will ensure that the new weather stripping adheres properly. Use a clean, dry cloth to wipe the surface clean.
Measure and Cut the New Weather Stripping Measure the length of the door jamb and cut the new weather stripping to fit. Be sure to leave a small amount of excess weather stripping so that it overlaps at the ends.
Install the New Weather Stripping Once you have cut the new weather stripping, peel off the backing to expose the adhesive. Carefully place the weather stripping onto the door jamb, starting at the top and working your way down. Be sure to press the weather stripping firmly against the door jamb to ensure a secure fit.
Check the Fit Test the fit of the new weather stripping by closing the door. The weather stripping should form a tight seal around the door. If there are any gaps or spaces, adjust the weather stripping as needed.
for such more question on stripping
https://brainly.com/question/20961968
#SPJ11
a pipeline constructed of carbon steel failed after 3 years of operation. on examination it was found that the wall thickness had been reduced by corrosion to about half the original value. the pipeline was constructed of nominal 100 mm (4 in) schedule 40, pipe, inside diameter 102.3 mm (4.026 in), and outside diameter 114.3 mm (4.5 in). estimate the rate of corrosion in ipy and mm per year.
In this scenario, a pipeline made of carbon steel failed after three years of operation due to corrosion. The wall thickness of the pipeline had reduced to about half of its original value. The pipeline was constructed of nominal 100 mm (4 in) schedule 40 pipe, with an inside diameter of 102.3 mm (4.026 in) and an outside diameter of 114.3 mm (4.5 in).
To estimate the rate of corrosion in IPY (inches per year) and mm per year, we need to use the following formula:
Rate of Corrosion = (Original Thickness - Remaining Thickness) / (Operation Time x Corrosion Allowance)
The original thickness of the pipeline can be calculated as:
Original Thickness = (Outside Diameter - 2 x Corrosion Allowance)
We know that the outside diameter of the pipeline is 114.3 mm (4.5 in) and the schedule 40 pipe has a corrosion allowance of 3.05 mm (0.12 in). Therefore, the original thickness can be calculated as:
Original Thickness = (114.3 mm - 2 x 3.05 mm) = 108.2 mm (4.26 in)
Now we can use the formula to estimate the rate of corrosion in IPY and mm per year:
Rate of Corrosion in IPY = (Original Thickness - Remaining Thickness) / (Operation Time x Corrosion Allowance)
Rate of Corrosion in IPY = (108.2 mm - 0.5 x 108.2 mm) / (3 years x 0.12 in)
Rate of Corrosion in IPY = 49.6 IPY
Rate of Corrosion in mm per year = (Original Thickness - Remaining Thickness) / (Operation Time x Corrosion Allowance)
Rate of Corrosion in mm per year = (108.2 mm - 0.5 x 108.2 mm) / (3 years x 3.05 mm)
Rate of Corrosion in mm per year = 4.8 mm/year
The rate of corrosion in IPY is estimated to be 49.6 IPY, and in mm per year, it is estimated to be 4.8 mm/year. These calculations help us to understand the rate at which the pipeline deteriorated due to corrosion, which can be used to prevent future failures and ensure the safety and longevity of similar pipelines.
To learn more about corrosion, visit:
https://brainly.com/question/20407861
#SPJ11
An orifice with a 50 mm in diameter opening is used to measure the mass flow rate of water at 20°C through a horizontal 100 mm diameter pipe. A mercury manometer is used to measure the pressure difference across the orifice. Take the density of water to be 1000 kg/m³ and viscosity of 1.003 x 10-³ kg/m-s. If the differential height of the manometer is read to be 150 mm, determine the following: a) Volume flow rate of water through the pipe b) Average velocity of the flow c) Head loss caused by the orifice meter d) What will be height of water column required if replaced with water manometer 100 mm 50 mm 150 mm
On the orifice with a 50 mm in diameter opening:
(a) The volume flow rate of water through the pipe is 3.375 m³/s.(b) The average velocity of the flow is 1.082 m/s.(c) The head loss caused by the orifice meter is 0.15 m.(d) The height of water column required if replaced with water manometer is 2.04 m.How to solve for the orifice?(a) The volume flow rate of water through the pipe is:
\(Q = A_v v\)
where A_v = area of the orifice and v = velocity of the flow.
The area of the orifice is:
\(A_v = \pi ( \frac{d}{2} )^2 = \pi (\frac{50}{2})^2 = 1962.5 mm^2\)
The velocity of the flow is:
\(v = \sqrt{2gH} = \sqrt{2(9.81)(0.15)} = 1.715 m/s\)
Therefore, the volume flow rate is:
Q = 1962.5 mm² × 1.715 m/s = 3.375 m³/s
(b) The average velocity of the flow is:
\(v_avg = Q/A_p = Q/(\pi (\frac{d}{2})^2) = 3.375 m^3/s / (\pi (\frac{100}{2})^2) = 1.082 m/s\)
(c) The head loss caused by the orifice meter is:
\(H_L = \frac{v^2}{2g} = \frac{(1.715)^2}{2(9.81)} = 0.15 m\)
(d) The height of water column required if replaced with water manometer is:
\(H_w = \frac{\rho_m}{\rho_w} H_m = \frac{13.6}{1} (0.15) = 2.04 m\)
Therefore, the answers to your questions are:
(a) The volume flow rate of water through the pipe is 3.375 m^3/s.
(b) The average velocity of the flow is 1.082 m/s.
(c) The head loss caused by the orifice meter is 0.15 m.
(d) The height of water column required if replaced with water manometer is 2.04 m.
Find out more on orifice here: https://brainly.com/question/30423172
#SPJ4
When the pressure relief valve in a system opens during work
Answer:
The relief valve will open as pressure caused by a downstream load or backpressure increases high enough to force the poppet or spool open against its spring.
Explanation:
1. Have you ever heard of the design process?
Answer:
Yes
Explanation:
The Design Process is an approach for breaking down a large project into manageable chunks.
what is 2+2 X56 JN BJJBJBJB
Answer:if u mean 2+2x56= 114 ...
Explanation:
Answer: 224
Explanation: 2+2 = 4
4 X 56 =224
Examine the pressure-measuring device shown in the figure below. (a) What is the gauge pressure reading in psi at point A? (b) What is the pressure difference between point A and B? (c) Which is higher, pressure at point A or at point B? (d) What is the absolute pressure in psi at point D? State any assumptions you made
Answer: 45
Explanation:just cuase I need to
a horizontal rigid bar abc is pinned at end a and supported by two cables at points b and c. a vertical local p
Sum of forces is zero and there is no resultant force .
Minimum cross sectional area can not be determined with the available information.
Given,
Vertical load = 10 kN
Modulus of elasticity = 200GPa
Yield stress on the cable = 400 MPa
Safety factor = 2.0
Now,
Let
L = \(\sqrt{(1.5)^{2} + (1.5)^2 }\)
L = 3.35 m
substituting 1.5 m for h and 1.5 m for the term (a + b)
Ф = tan⁻¹(1.5/1.5)
Ф = 45⁰
Substituting 1 for h and 3 m for (a+ b) yields:
Ф = tan⁻¹(1/3)
Ф = 25.56⁰
Since the sum of the forces is zero, the system is balanced and there is no resultant force.
Know more about modulus of elasticity,
https://brainly.com/question/32227157
#SPJ4
What is the eye an example of?
sense organ
stimulus
a relay neuron
sens organ is the eye example
A short transmission line connects a step-up transformer on the source side with a series impedance of j0.5 ohms (referred to the primary) to a step-down transformer on the load side with a series impedance of 50 ohms (referred to the primary). the turn ratio of the step-up transformer is 1:14 and a no-load primary voltage of 17 (line-to-line) kv. the step-down transformer has a turn ratio of 18:1 and it has a y-connected, balanced load of 0.463 j 0.0772 ohms connected to its secondary side. a capacitor bank of -j0.324 ohms is added parallel to the load. assuming an ideal transmission line, the effective impedance (per phase) of the system seen by the source would be:
The effective impedance (per phase) of the system seen by the source, assuming an ideal transmission line, would be:
Z_src = j0.5 + (50/14) + (18/14)(0.463 + j0.0772 + (-j0.324)) = j0.5 + 3.571 + 0.848 = 4.419 + j0.5
The effective impedance (per phase) of the system seen by the source for the given setup would be 4.419 + j0.5 Ω, when a capacitor bank of -j0.324 Ω is added parallel to the load.
This is calculated by taking the total impedance of the load side (50 Ω) and the transmission line (j0.5 Ω) referred to the primary side of the step-up transformer (1:14 turn ratio) and then adding the parallel capacitor (-j0.324 Ω).
Learn more about The effective impedance of the system seen:
https://brainly.com/question/14931545
#SPJ4
consider a stokes flow due to a sphere rotating near a wall, argue from kinematic reversibility weather or not the rotating sphere will experience a force pushing it away or drawing it into the wall
In Stokes flow, the fluid velocity is proportional to the forces acting on the fluid and the fluid is assumed to be viscous and incompressible. The fluid velocity near a rotating sphere in Stokes flow can be determined using the equations of fluid dynamics.
What is the reversibility about?Kinematic reversibility is a property of Stokes flow, which states that the fluid flow is symmetric with respect to time reversal. This means that if the fluid velocity is recorded at a certain time, then the same velocity field will be obtained if time is reversed and the flow is replayed in the reverse direction.
When a sphere is rotating near a wall, the flow of fluid around the sphere creates a velocity field that pushes the sphere away from the wall. This flow can be considered as the fluid being pushed away from the sphere and towards the wall. If the flow is time-reversed, the fluid velocity field would be the same, but the direction of the velocity would be reversed. This means that the fluid would be drawn towards the sphere and away from the wall, pulling the sphere towards the wall.
Therefore, based on the property of kinematic reversibility in Stokes flow, the rotating sphere near a wall will experience a force that could either push it away from the wall or draw it towards the wall, depending on the direction of the flow.
Learn more about reversibility from
https://brainly.com/question/3454191
#SPJ1
A feeder circuit with no motor lead has a continuous load of 5A and a noncontinuous load of 5A. the feeder overcurrent protective device should be sized at
11.25A
Electric illumination, process pumps and compressors needed to meet the design flow conditions, and either space heating or air conditioning, whichever is larger, are examples of continuous loads.
What A feeder circuit with no motor lead has continuous?An ampere rating for circuit breakers is often noted on the operational handle's end. The breaker can handle this amount of continuous current up to its rating without failing. Generally speaking, the ampere rating of the circuit breaker should match the capacity of the line.
Therefore, the feeder overcurrent protective device should be sized at
11.25A
Learn more about feeder circuit here:
https://brainly.com/question/28314982
#SPJ1
Running ropes must be taken out of service if they have _____ broken wires in one strad in one lay
Answer:
3
Explanation:
3 broken wires in one strand in one lay are cause for removal from service.
Answer:
3Running ropes must be taken out o service if they have 3 broken wires in one strand in one lay.1. The term lefty loosey, righty tighty is used to prevent what?
Answer:
Used to recall the direction a standard screw
A large gas-turbine power plant delivers a net power output of 325 MW to an electric generator. The minimum temperature in the cycle is 300 K, and the maximum temperature is 1500 K. The minimum pressure in the cycle is 100 kPa, and the compressor pressure ratio is 12. Calculate the power output of the turbine, the back work ratio, and the thermal efficiency of the cycle. Also, determine the improved thermal efficiency if a regenerator, with an effectiveness of 85 percent, were installed in the power plant.
Answer:
A) Power output = 541.67 MW
B) Backwork ratio = 0.4
C) Improved thermal efficiency = 0.598
Explanation:
We are given;
Net power output; W'_net = 325 MW
Minimum Temperature; T1 = 300 K
Maximum Temperature; T4 = 1500 K
Compression Pressure ratio;P2/P1 = 12
From online tables, we have the following properties of air;
Specific heat capacity; C_p = 1.004 KJ/Kg
Adiabatic constant; k = 1.4
Temperature at stage 2 will be given by the formula;
T2 = T1(P2/P1)^((k - 1)/k)
Plugging in the relevant values gives;
T2 = 300(12)^((1.4 - 1)/1.4)
T2 = 610.18 K
Similarly, Temperature at stage 3 will be;
T3 = T4(P2/P1)^((k - 1)/k)
Plugging in the relevant values gives;
T3 = 750(12)^((1.4 - 1)/1.4)
T3 = 1525.45 K
Now, let's calculate the specific heat addition given by the formula;
q = C_p(T3 - T2)
q = 1.004(1525.45 - 610.18)
q = 918.93 KJ/Kg
Let's now calculate the specific net work output;
w_net = C_p[(T3 - T4) - (T2 - T1)]
w_net = 1.004[(1525.45 - 750) - (610.18 - 300)]
w_net = 467.13 KJ/Kg
A) Power output is given by;
W_T = (W'_net/W_net) × C_p(T3 - T4)
W_T = (325/467.13) × 1.004(1525.45 - 750)
W_T = 541.67 MW
B) back work ratio is;
f = (T2 - T1)/(T3 - T4)
f = (610.18 - 300)/(1525.45 - 750)
f = 0.4
C) Thermal efficiency is given by;
η = w_net/q
Since we are told that a regenerator, with an effectiveness of 85 percent, were installed in the power plant.
Thus;
η = (w_net/q)÷0.85
η = (467.13/918.94) ÷ 0.85
η = 0.598
Technician a says kinetic friction changes kinetic energy into thermal energy. technician b says static friction holds the car in place when it is stopped. who is correct?
Technician a says kinetic friction changes kinetic energy into thermal energy. technician b says static friction holds the car in place when it is stopped. Both A and B are correct.
What is kinetic and static friction?In static friction, there is found to be some frictional force that tends to resists force that is known to be applied to an object, and the object will be at the same sport at rest until the force of static friction is known to be overcome.
In kinetic friction, the frictional force is one that tend to resists the movement of an object.
Therefore, Technician a says kinetic friction changes kinetic energy into thermal energy and technician b says static friction holds the car in place when it is stopped. Both A and B are correct.
Learn more about kinetic friction from
https://brainly.com/question/14111192
#SPJ1
A student made a table comparing erosion caused by glaciers and hurricanes. Is the table correct?
Glaciers Hurricanes
The movement of glaciers causes rocks to move
Occurs slowly The strong winds and waves common to hurricanes causes sand to move
Occurs quickly
Yes, because both forms of erosion involve the movement of rocks and soil.
No, because erosion always occurs quickly.
Yes, because erosion is a process that only involves water.
No, because only hurricanes use their movement to cause rocks and soil to move.
Answer: A. yes
Explanation:
Which statement contains valid syntax for the RETAIN statement?
a. retain Year 2018;
b. retain Year*2018;
c. retain Year=2018;
d. retain Year{2018};
The statement that contains valid syntax for the RETAIN statement is c. retain Year=2018;
a. retain Year 2018;
This statement will retain the value of the variable Year from the previous observation and initialize it to 2018 for the first observation in the data step. The other options provided do not have valid syntax for the RETAIN statement in SAS.
b. retain Year*2018; - This statement contains an invalid syntax for the RETAIN statement in SAS. The asterisk symbol cannot be used as a separator between the variable name and its initial value.
c. retain Year=2018; - This statement contains an invalid syntax for the RETAIN statement in SAS. The equal sign cannot be used as a separator between the variable name and its initial value.
d. retain Year{2018}; - This statement contains an invalid syntax for the RETAIN statement in SAS. The curly braces are not used to specify the initial value of a variable in the RETAIN statement
To know more about RETAIN visit:
https://brainly.com/question/13980094
#SPJ11
What happens to the speed of light if the IOR increases?
The principal disadvantages(s) with the waterfall development methodology is (are) _____.
a. a long time elapses between completion of the system proposal and the delivery of the system
b. if the team misses important requirements, expensive post-implementation programming may be needed
c. the design must be completely specified on paper before programming begins
d. all of the above
e. none of the above
Note that the principal disadvantage (s) with the waterfall development methodology is (are) "All the Above" (Option D).
What is the Waterfall Development Methodology?The Waterfall Development Methodology is a process for creating software that involves a series of steps that are followed in a specific order. It is called the "waterfall" method because each step flows into the next, like water flowing down a waterfall.
The first step in the Waterfall Development Methodology is to gather requirements, which means figuring out what the software should do. Next, a design is created, which outlines how the software will look and work. Then, the software is actually developed, which means writing the code and creating the software. After that, the software is tested to make sure it works correctly and any problems are fixed. Finally, the software is deployed, which means it is made available for people to use.
Learn more about the Waterfall Methodology:
https://brainly.com/question/28750057
#SPJ1
What does a restriction in the fuel return line cause?
Answer:
Carburetor flooding, engine stalling, and hard starting
Explanation:
If the fuel return hose becomes blocked or kinked it may cause the carburetor to flood from excessive fuel or pressure buildup.
37. In ______ combination of drugs, the effects of one drug cancel or diminish
the effects of another.
A.additive
B.antagonistic
C.synergistic
D.energetic
(For drivers ed btw)
Answer:
In antagonistic combination of drugs, the effects of ine drug cancel or diminish the effects of another