Probability Calculation: The critical path for a project was found to be 37 days. The variances total 27. What is probability of completing in 43 days

Answers

Answer 1

Answer:

0.1241

Step-by-step explanation:

Given that:

Critical path = 37 days

Variance total = 27 days

Completion date (x) = 43 days

We obtain the Zscore :

Zscore = (x - critical path) / variance total

Zscore = (43 - 37) / √27

Zscore = 6 / √27

Zscore = 1.1547

Zscore = 1.155

Hence, probability of completing in 43 days :

P(Z > 43) = 1 - P(Z < 43)

P(Z < 43) = 0.8759

P(Z > 43) = 1 - 0.8759 = 0.1241


Related Questions

A number is between 40 and 45 . It has prime factors of 2 and 11. What is the ​ number?

Answers

Answer: 42

Step by step:

42 is divisible by both 7 and 2

Answer:

44

Step-by-step explanation:

4 x 11 = 44

2 x 22 = 44

PLS HELP ASAPPP
I really need help

question: write in standard form.

2x^2+x^3-3+4x^5

PLS HELP ASAPPPI really need help question: write in standard form. 2x^2+x^3-3+4x^5

Answers

Answer:

4x^5 + x^3 + 2x^2 -3

Step-by-step explanation:

Standard form is ( put simply ) the order the numbers are from highest to lowest. So the standard form of the equation would be 4x^5 + x^3 + 2x^2 -3

4x^5 +x^3+2x^2−3

hope this helps!

Music students and art students at a middle school were surveyed to choose a cardiovascular activity: playing sports or dancing.


Do you prefer dancing or playing sports?
Playing sports Dancing Row totals
Music students 32 15 47
Art students 31 22 53
Column totals 63 37 100


What is the marginal frequency of students who chose dancing?
15
22
37
53

Answers

The marginal frequency of students who chose dancing is 37.

The correct answer to the given question is option 3.

The marginal frequency of students who chose dancing can be calculated by adding up the number of students who chose dancing in each row or column. In this case, we need to add up the number of art students who chose dancing (22) and the number of music students who chose dancing (15), which gives us a total of 37. This is the marginal frequency of students who chose dancing.

Based on the survey results, it appears that a slightly higher percentage of art students prefer dancing (41.5%) compared to music students (31.9%). However, both groups of students seem to be fairly evenly split between dancing and playing sports, with a slight preference for playing sports overall.

It's worth noting that cardiovascular activity is important for overall health and well-being, and both dancing and playing sports can provide great opportunities for exercise and physical activity. Additionally, both activities can also be enjoyable and provide a sense of community and social connection, which is important for middle school students who are still developing their social skills and relationships. Ultimately, the choice between dancing and playing sports will depend on individual interests, preferences, and abilities.

For more such questions on frequency, click on:

https://brainly.com/question/254161

#SPJ8

I neead a fast answer 50pts fast (+Brainliest for right answer)!!!!

I neead a fast answer 50pts fast (+Brainliest for right answer)!!!!

Answers

Answer: The description of that transformation is the triangle is rotated 90 degrees clockwise. Then, it's moved to the right TWICE. Finally, you go down 2 times.

Step-by-step explanation:

Hope this helps :)

triangle B is in dofferent orientation from triangle B so we know it was either mirrored or rotated. Triangle B isnt in the exact opposite orientation as A so we know it wasnt mirrored. So we now know that it was rotated and know we have to find the point of rotation. we can tell that the rotation was 270 degrees anti clockwise since it cant be clockwise because no points of rotation match. since we know triangle A was rotated 270 degrees anti clockwise to get triangle B we cant find the point of rotation by seeing which point works and if we test the points we will see that (0;-1) is the point of rotation. So triangle A was rotated 270 degrees anti clockwise on the point (0;-1) to make triangle B

For each of the following, identify the exam score that should lead to the better grade. In each case, explain your answer.

a) A score of X = 74 on an exam with μ=82 and σ=8; or a score of X = 40 on an exam with μ=50 and σ=20.
b) A score of X = 51 on an exam with μ=45 and σ=2; or a score of X = 90 on an exam with μ=70 and σ=20.
c) A score of X = 62 on an exam with μ=50 and σ=8; or a score of X = 23 on an exam with μ=20 and σ=2.

Answers

The exam scores , that will lead to the better grade is

(a) the score of "X=40" in exam with μ = 50 , σ = 20 ;

(b) the score of "X=51" in exam with μ = 45 , σ = 2 ;

(c) Both the score will lead to better grades .

Part(a) : In order to find which score leads to better grade, we calculate the z-scores for both scores and compare :

The score of X = 74 on the first exam is :

⇒ z = (74 - 82)/8 = -1  ;

The score of X = 40 on the second exam is :

⇒ z = (40 - 50)/20 = -0.5  .

The z-score of -0.5 is > -1,

So , the score of X = 40 on the second exam lead to better grade because the score of 40 is closer to mean of second exam (50) and has a smaller deviation from mean (20) than score of 74 on first exam .

Part(b) :

The score of X = 51 on the first exam is :

⇒ z = (51 - 45)/2 = 3  ;

The score of X = 90 on the second exam is :

⇒ z = (90 - 70) / 20 = 1  .

The z-score of 3 is > 1 ,

So , the score of X = 51 on the first exam should lead to the better grade.

Part(c) :

The score of X = 62 on the first exam is :

⇒ z = (62 - 50) / 8 = 1.5  ;

The score of X = 23 on the second exam is :

⇒ z = (23 - 20) / 2 = 1.5  .

Both scores have the same z-score of 1.5, they should lead to the same grade.

Learn more about Z-Score here

https://brainly.com/question/15016913

#SPJ4

Between which two consecutive integers is \(\sqrt{201}\)

Answers

Answer:

14 and 15

Step-by-step explanation:

\(196<201<225 \\ \\ \sqrt{196}<\sqrt{201}<\sqrt{225} \\ \\ 14<\sqrt{201}<15\)

Kevin's bank deducts a service fee from his account every month.
In one year, the bank deducts a total of $90 in fees. Twice each
month, Kevin's paycheck is directly deposited into his account.
The amount of each paycheck is $1,150. Which expression
represents the monthly change in Kevin's bank account?

Answers

The expression that represents the monthly change in Kevin's bank account is $2,300 - $7.50 = $2,292.50

How to find the expression

In one year, which has 12 months, the bank deducts a total of $90 in fees. To find the monthly change in Kevin's bank account, we need to divide this total by 12:

Monthly service fee = $90 / 12 = $7.50

Kevin's paycheck is deposited twice each month, so his total monthly income from his paychecks is:

Monthly income = 2 * $1,150 = $2,300

Therefore, Kevin's monthly change in his bank account is:

Monthly change = Monthly income - Monthly service fee

Monthly change = $2,300 - $7.50 = $2,292.50

So the expression that represents the monthly change in Kevin's bank account is $2,300 - $7.50 = $2,292.50

Learn more about  expression at:https://brainly.com/question/1859113

#SPJ1

When graphed in the (x,y) coordinate plane, at what point do the lines x - y = 12
and y= 2 intersect?

Answers

Answer:

(14, 2).

Step-by-step explanation:

x - y = 12

y = 2

Solving this system:

Plug y = 2 into the first equation:

x - 2 = 12

x = 14.

Therefore the  point of intersection is at (14, 2).

please answer or i move down grade again

please answer or i move down grade again

Answers

Answer:

x is a 33° angle

Step-by-step explanation:

The two angles are supplementary meaning the measure of both angles adds up to 180°. You can tell they are supplementary because the angle is a straight line. so all you need to do is subtact 147 from. 180 to get the measure of x .

Answer:

x+147=180 ( sum of supplementary angle)

or, x = 180-147

or, x = 33

so the value of x is 33°

Pablo used a total of 5 3/4 gallons of gas while driving his car. Each hour he was driving, he used 5/6 gallons of gas. What was the total number of hours he was driving? Write your ans

Answers

Let x be the number of hours Pablo was driving.

We know that he used 5/6 gallons of gas per hour of driving.

So, the total amount of gas he used is 5/6 * x.

We also know that he used a total of 5 3/4 gallons of gas.

So, we can set up the equation:

5/6 * x = 5 3/4

To solve for x, we can first convert 5 3/4 to an improper fraction:

5 3/4 = 23/4

Then, we can multiply both sides of the equation by the reciprocal of 5/6:

x = (5 3/4) / (5/6)

x = (23/4) / (5/6)

x = (23/4) * (6/5)

x = 27.6/4

x = 6.9

Therefore, Pablo was driving for a total of 6.9 hours.

brainliest???

I NEED HELP PLSSSSSSSS

I NEED HELP PLSSSSSSSS

Answers

Answer:

X >>>>> Y

–1 >>>> 16

0 >>>>> 8

1 >>>>> 4

2 >>>>> 2

3 >>>>> 1

Step-by-step explanation:

From the question given above,

y = 8 × (½)ˣ

When x = –1, y =?

y = 8 × (½)ˣ

y = 8 × (½)¯¹

y = 8 × 2

y = 16

When x = 1, y =?

y = 8 × (½)ˣ

y = 8 × (½)¹

y = 8 × ½

y = 4

When x = 2, y =?

y = 8 × (½)ˣ

y = 8 × (½)²

y = 8 × ¼

y = 2

When x = 3, y =?

y = 8 × (½)ˣ

y = 8 × (½)³

y = 8 × ⅛

y = 1

SUMMARY:

X >>>>> Y

–1 >>>> 16

0 >>>>> 8

1 >>>>> 4

2 >>>>> 2

3 >>>>> 1

Which is misleading about the data shown on the figure?
Number of members
Look at the photo

Which is misleading about the data shown on the figure?Number of membersLook at the photo

Answers

The misleading about the data shown on the figure is the clas width

Which is misleading about the data shown on the figure?

From the question, we have the following parameters that can be used in our computation:

The histogram

On the histogram, we have the following readings

1 - 2021 - 3031 - 4546 - 65

From the above, we can see that

The above readings are not consistent i.e. the class widths are not equal

Hence, the misleading about the data shown on the figure is the clas width

Read more about graphs at

https://brainly.com/question/28350999

#SPJ1

34 miles
30 mph
How much time will it
take for these two
vehicles to meet?
55 mph
[?] hours

34 miles30 mphHow much time will ittake for these twovehicles to meet?55 mph[?] hours

Answers

Answer:

0.4 hours

Step-by-step explanation:

or 24 minutes :D

1) There are 56 people at a party. Each table has 8 seats. How many tables are
needed so all of the people have a seat?
56 +
= 8
6
54

Answers

Answer:

56 / 8

Step-by-step explanation:

Find the Prime Factorization of -165

Answers

Answer:

(-1)(11)(3)(5)

Step-by-step explanation:

First off:  -165 separates into the factors (-1) and (165).  Next, we divide 165 by 15, obtaining 15(11).

So far, we have (-1)(11)(15).

15 is still factorable.  We get:

(-1)(11)(3)(5), which is the desired prime factorization of -165.

What is f(4) for the function f(x)= 6x+7?

What is f(4) for the function f(x)= 6x+7?

Answers

Answer:

31

Step-by-step explanation:

f(4) = 6x4 + 7

= 24 + 7

= 31

god gave me 3 apples but the devil would have gave me 23 have many apples do i have?

Answers

3 because the devil never actually gave you the apples. He would have but didn’t.

A state lotto has a prize that pays $900 each week for 20 years.
Find the total value of the prize: $

If the state can earn 5% interest on investments, how much money will they need to put into an account
now to cover the weekly prize payments?

Reminder: There are 52 weeks in a year.

Answers

The total value of the prize is $936,000.

The state will need to invest $591,498.96 now at a 5% interest rate to cover the weekly prize payments for 20 years.

What is the total value of the prize?

The total value of the prize is calculated by multiplying the annual payment by the number of years and is equal to:

=  $900/week x 52 weeks/year x 20 years

= $936,000.

How much money is needed to put into the account?

We need to use the present value formula which is: PV = PMT x [1 - (1 + r)^-n] / r

Plugging in the values:

PV = $900 x [1 - (1 + 0.00096154)^-1,040] / 0.00096154

PV = $900 x 657.221075423

PV = $591,498.968.

Read more about state lotto

brainly.com/question/28988219

#SPJ1

What number decreased by 40 is 5 times that number?

Answers

Answer:

-10

Step-by-step explanation:

Let the number be x

x - 40 = 5x

⇒ -40 = 5x - x

⇒ 4x = -40

⇒ x = -40/4

⇒ x = -10

Answer:

-10

Step-by-step explanation:

Let the number be x

x - 40 = 5x

4x = -40

x = -10

Definitions for vocab

Definitions for vocab

Answers

Just search the definitions

Answer:

when whered then they

Step-by-step explanation:

How to solve this 75,465(7)

Answers

Based on context clues or what's been given,

Parenthesis indicate multiplication.

75,465 * 7

Now calculate:

528,255

Answer: 528,255

Step-by-step explanation:

u just multiply 75,465 by 7 and you get 528,255


if there is a number next to another number that is inside the parentheses then that means you multiply the numbers together


for example: 12(3) means multiply 12 by 3 and u get 36

3/16 divided by 2 1/4

Answers

I got 0.0833333 that’s what I got

NEED HELP!! I"LL GIVE YOU BRAINLIEST!! Find the value of b. a = 3 and c =12

NEED HELP!! I"LL GIVE YOU BRAINLIEST!! Find the value of b. a = 3 and c =12

Answers

Answer: b = 11.62

Step-by-step explanation:

We can use this formula to solve for b:

\(b^{2} =\) \(\sqrt{c^{2}-a^{2} }\)

\(b^{2} =\) \(\sqrt{12^{2}-3^2 }\)

\(b^2= \sqrt{144-9}\)

= 11.61895004

We can round that to 11.62.

Hope this helped!

Factor. Please show work

Factor. Please show work

Answers

Answer:

Step-by-step explanation:

f(x)=2(2x+3)(x−3)
hope this helps

what is the solution for 96 = 12d?

Answers

d = 8

Divide both sides of the equation by the same term

Answer:

d = 8

Step-by-step explanation:

Step 1: Divide both sides by 12.

\(12d/12 = 96/12\) \(d=8\)

Therefore, the solution is 8.

Questions
1. There are 30 students in a class: 16 boys and 14 girls. What is the probability that a boy will be chosen at random?
2. A bag contains 3 green marbles, 6 blue marbles and 6 red marbles. One marble is taken out of the bag at random.
What is the probability of choosing:
(1) a red marble?
a
(11)
a green marble?
3.
(a) What is the probability of choosing the letter B at random from the word ALPHABET?
+

Answers

Answer:

1. 8/15

2. Green marble: 3/15

    Red Marble: 6/15

     Blue marbles: 6/15

3. a 1/8

Answer:

1: 8/15

2: a: 2/5

 b: 1/5

3: 1/8

Step-by-step explanation:

1:

16/30 chance

simplify

8/15

2:

3 + 6 + 6 = 15

red: 6/15 --> 2/5

green: 3/15 --> 1/5

3:

1/8

Solve 4(x - 3) - 2(x - 1) > 0.
OXIX > 2)
OxIx>7)
Oxlx> 14)
O x 1 x>5)

Answers

Answer:

4(x - 3) - 2(x - 1) > 0

(4x - 12) - 2x  + 2) > 0

4x - 2x - 12 + 2 > 0

2x - 10 > 0

2x > 10

x > 10/2

x > 5

If 3220 = 8+7, what is the value of c?
01
02
03
05

Answers

Answer:

c = 3

Step-by-step explanation:

\( 32^{2c} = 8^{c + 7} \)

\( (2^5)^{2c} = (2^3)^{c + 7} \)

\( 2^{10c} = 2^{3c + 21} \)

\( 10c = 3c + 21 \)

\( 7c = 21 \)

\( c = 3 \)

A man wants to mesure the height of a nearby building. He places a 7ft pole in the shadow of the building so that the shadow of the pole is exactly covered by the shadow of the building. The total length of the building’s shadow is 162ft, the pole casts a shadow that is 5.5ft long. How tall is the building? Round your answer to the nearest foot.

Answers

The height of the building is approximately 227 feet.

In the given question, a man wants to measure the height of a nearby building. He places a 7 ft pole in the shadow of the building so that the shadow of the pole is exactly covered by the shadow of the building.

The total length of the building's shadow is 162 ft, and the pole casts a shadow that is 5.5 ft long. We have to determine the height of the building.The given situation can be explained with the help of a diagram.

As shown in the figure above, let AB be the building and CD be the 7 ft pole. The height of the building is represented by the line segment AE, which is to be determined. Let the length of the shadow of the pole be CD and that of the building be BD.

Therefore, the length of the total shadow will be BC or CD + BD.According to the question, the shadow of the pole is exactly covered by the shadow of the building. This implies that the two triangles AEF and CDF are similar. Hence, the corresponding sides are proportional. Therefore, we have:AE/EF = CD/DF

On substituting the values from the given data, we get:

AE/(EF + 5.5) = 7/5.5.... (1)

Similarly, we can write from the given data:

BD/DF = 162/5.5.... (2)

From equations (1) and (2), we can write:

AE/(EF + 5.5) = BD/DF => AE/(EF + 5.5) = 162/5.5.... (3)

On solving the above equation for AE, we get:

AE = (7/5.5) × (162/5.5 - 5.5)≈ 226.6 ft

Therefore, the height of the building is approximately 227 feet.

For more such questions on height, click on:

https://brainly.com/question/28122539

#SPJ8

Joe says 4.02 times 0.3 is about 12. Does this make sense? Explain your thinking.

Answers

Answer:

No, it doesn't.

Because 0.3 is smaller than 1, so the product should be less than 4.02.

Let me know if this helps!

Other Questions
What is the volume of this container 4 ft2 2 ft3 2 ft2 4 ft3 In contrast to bureaucratic controls, market controls involve the use of:A.rules and regulations.B.economic forces.C.authority.D.autocratic power.E.norms. A chemical company makes two brand of anitifreeze. first brand is 45% pure anitifreeze , and the second brand is 70% pure anitifeeze in order to obtain 60 gallons of a mixture that contains 65% pure antifreeze , how many gallons of each brand of antifreeze must be used What contributed to the economic success of great zimbabwe?its valuable copper mines(wrong)its location on the nile riverits location as a port cityits commercial links with coastal cities 1How does the author build suspense in paragraph 12?A By having Vincent question his resolveB By describing Vincent squinting at the audienceC By causing Vincent to reveal his physical discomfortD By providing details about the audience at the meeting, jill informed the logistics manager that a new advertising campaign was being rolled out in june and an increase in sales for the active-wear line was expected. which of the four ps is affecting logistics in this situation? multiple choice question. price plan place promotion product A kite is flying 10 ft. in the air. The angle ofelevation is 20. How long is the kite string? find the domain for y=5x determine if it's a function what is the role of pleiotropic transcription factors in cancerdevelopment? Reducing restaurant food waste 1 what is the problem? what caused the problem? what recommendations can be made? how is this relevant to the restaurant hospitality industry? The amount of coffee that people drink per day is normally distributed with a mean of 17 ounces and a standard deviation of 6.5 ounces. 35 randomly selected people are surveyed. Round all answers to 4 decimal places where possible.Find the IQR for the average of 35 coffee drinkers.Q1 = ouncesQ3 = ouncesIQR: ounces Does the inheritance of eye color depend on the inheritance of fur color in mice type of species that can respond to changes in the environment better. Prompt #1 What converging social, economic, and environmental factors likely caused the Late Bronze Age collapse of many different civilizations in the Mediterranean world around 1250-1150 BC, and how were these factors related to one another? Which of these major factors seem to have been more long-term, and which of these factors seem to have been a more immediate cause of this widespread collapse? Be sure to provide specific archaeological evidence from Egyptian, Mycenaean, Minoan, and/or other relevant civilizations illustrating the effects of the factors you identify, and spend at least part of your response explaining in detail how/why archaeologists think some of these distinct causes may have been related to (or a result of) one another. How do we find the constant rate from two points? (Write yourself step by stepdirections to do this) How to Cite a PDF in APA? who are budoiuns why do they for a living What fraction is equal to 0.37? Some secretory proteins and some integral membrane proteins must pass through a membrane.a. Trueb. False During the first year with a company, Finley was paid an annual salary of $57,000, with a 4% raise for each following year. Which equation represents Finley's annual salary, f (n), during the nth year? f (n) = 57,000(0.04n 1) f (n) = 57,000(1.04n) f (n) = 57,000(1.04n 1) f (n) = 57,000(0.96n)